Extends the construction deadline on the Jennings Randolph Hydroelectric Project located on the North Branch of the Potomac River for up to six years.
Official Summary
Passed House
2017-06-12
Passed Senate
2018-06-28
Signed by President
2018-07-23
Became Public Law
2018-07-23
Amendments
None.
Sponsors
Original sponsor: Rep. McKinley, David B. [R-WV-1]
Cosponsors: Rep. Delaney, John K. [D-MD-6]
Votes
Passed House by voice vote.