
Seal of the U.S. Department of Energy’s Federal Energy Regulatory Commission (FERC).
Authorizes FERC to extend the construction deadline on the Gathright Hydroelectric Project in Alleghany County, Virginia for up to six years.
Official Summary
Passed House
2017-06-12
Passed Senate
2018-06-28
Signed by President
2018-07-23
Became Public Law
2018-07-23
Amendments
None.
Sponsors
Original sponsor: Rep. Griffith, H. Morgan [R-VA-9]
Votes
Passed House by voice vote.
Passed Senate by unanimous consent.